DELTA COATINGS ON STAGE AT PDA Europe Conference 2025 – Bournemouth, UK

A proud moment for DELTA Coatings as our CEO,

Belvin Marx
,
took the main stage to deliver a specialist technical seminar on one of our most iconic achievements: the

Dubai Fountain


Polyurea

Refurbishment Project, completed ahead of schedule in September.

This landmark project showcased the power of engineering expertise, large-scale execution capability, and our advanced
DELTAShield Aqualine AL system — designed specifically for high-performance waterproofing of mega-structures.

⛲ Project Fast Facts — Dubai Fountain (Aqualine AL)

  • Surface area: 100,000 m²
  • Project duration: 180 days
  • Coating window: 90 days
  • Zonal division: 12 zones
  • Manpower: 400 labour + 50 management
  • Equipment: 12 Graco Reactor machines, 24 hydroblasting guns

Products applied:

  • DELTAprime 2KSF primer
  • DELTAprime Filler
  • DELTAShield Aqualine AL (3 mm DFT)

Daily productivity: 4,800 m²/day

⚡ Speed of Completion — Engineered for Fast Delivery

As one of the world’s most visited attractions, the Dubai Fountain could not be taken offline for long. The coating stage
required precise execution within a strict 90-day window aligned with the start of the tourist season.

Aqualine AL’s ultra-fast curing technology made this possible:

  • Touch dry: 10–20 seconds
  • Walkable: 10 minutes
  • Full chemical resistance: 12–24 hours

This rapid-curing performance allowed our teams to move seamlessly across all 12 zones, achieving up to
4,800 m² per day and handing over the fountain ahead of schedule, enabling additional testing time for the client.

🇪🇺 DELTA & PDA Europe — Advancing Global Polyurea Standards
As a long-standing and active member of PDA Europe, DELTA Coatings is proud to work alongside the association in educating
architects, specifiers, engineers, and industry leaders on the superior performance characteristics of polyurea-based
coating systems.